ELABORATION OF A UNIFIED ENVIRONMENTAL MONITORING PROGRAM NATURAL WATERS USED FOR TECHNICAL WATER SUPPLY NPP TO COMMISSIONING (FOR EXAMPLE BALTIC NPP)
- Authors: Luneva EV1
-
Affiliations:
- “Directorate for Construction of Baltic NPP”
- Issue: No 3 (2015)
- Pages: 78-86
- Section: Articles
- URL: https://journals.rudn.ru/ecology/article/view/12859
Cite item
Full Text
Abstract
The paper analyzes approaches to environmental monitoring of natural and artificial water bodies used in the technological cycle NPP, as well as approaches to observation reservoirs Russian NPPs under construction. Proved that in research there is no single comprehensive approach. Proposed a structure a unified program of environmental monitoring of natural water bodies, intended to be used for nuclear power plants supply prior to commissioning the example of the Baltic NPP
About the authors
E V Luneva
“Directorate for Construction of Baltic NPP”Branch of JSC “Concern Rosenergoatom”